Laying and handling guide

High voltage cables: laying and handling

IEC 60840 and IEC 62067 cables, 45 kV and above.

Every line names every source that states it and how it was seen; where sources disagree, each value is shown with its source. IEC, EN and HD documents and makers come first, national rules after them with their country.

Laying temperature and pre-warming

No value from a standard was found: use the maker's datasheet.

  • Nexans: Warm at +10 °C or more for at least 24 hours, then unreel within 2 hours at about 20 m/min; below -5 °C outside, postpone the pull or warm the drums first.Sources: Nexans 2021 p. 11 (maker's document)

Laying in winter? Pro checks your town and month against this limit. See Pro

Bending radius

  • IEC 60840, IEC 62067: Gives no installation bending radius; the values below come from makers.Sources: IEC 60840 text searched (read in the standard text)
  • TFK, 60 to 400 kV: 25 D while laying.Sources: TFK pdf 35 to 46 (maker's document)
  • Prysmian UK, 66 kV and above: About 30 D as a minimum.Sources: Prysmian UK p. 1 (maker's document)

National rules

  • Türkiye EKAT Çizelge-20: Three-core LV (XLPE or PVC) 12 D; three-core MV 15 D; armoured 15 D; single core 15 D.Sources: EKAT Madde 58 b) 9 (read in the standard text)

Pulling force and method

  • TFK: On the conductors: 50 N/mm² for copper, 30 N/mm² for aluminium.Sources: TFK pdf 35 to 46 (maker's document)
  • Nexans: A pulling eye on the conductors instead of a stocking for lengths over 800 m or conductors over 630 mm².Sources: Nexans 2021 p. 13 (maker's document)
  • Southwire: Work out the tension section by section (straights, slopes, bends) and the sidewall pressure at every bend, and pull from the end that gives the lower maximum.Sources: Southwire 2005 pp. 13 to 17 (maker's document)
  • Watch the tension all through a machine pull and keep the record with the as-laid documents. Prysmian: a winch with a dynamometer, a preset maximum and automatic stop; Draka: without a tension record the maker may refuse a claim.Sources: HD 620 Part 1 A.4.4; HD 603 3-G 3.3; IS 1255 10.3.5; Prysmian 2024 p. 10; Nexans 2021 p. 16; Draka p. 8 (read in the standard text)
  • Sidewall pressure: the maker's limit, checked before the pull at every bend, roller and deflection point; too much tears the sheath.Sources: BS 7846 A.7.4 d); Nexans 2021 p. 17; Anixter Sec. 20 p. 20-44 (read in the standard text)

Work out the pull for your route: the verdict is free, the numbers and the PDF come with Pro. Pull calculation in the cable designer · See Pro

Depth, cover and laying

Snaking in tunnels and troughs: no numbers (amplitude, pitch) were found; CIGRE TB 194 describes the method.

Not found in the research for this family.

  • Nexans: Thermal backfill: keep the specified thickness below and above and the trench width along the whole route, and never mix it with native soil, or the cable overheats.Sources: Nexans 2021 pp. 18 to 19 (maker's document)

Drum handling

  • Keep the drum upright, its axis horizontal, in storage and in transport; never lay it flat on a flange.Sources: HD 620 Part 1 A.3.2.5, A.3.3.2; IS 1255 7.7, p. 25; Prysmian 2024; Reka (read in the standard text)
  • Never drop a drum. Without lifting gear, use a ramp of about 1:4 (IS 1255: 1:3 to 1:4) with ropes or a winch and a sand bed at the foot.Sources: HD 620 Part 1 A.3.3.3; HD 603 3-I 3.3; IS 1255 7.3, p. 24; Prysmian 2024 p. 6; Reka p. 6; Nexans 2021 p. 4 (read in the standard text)
  • Roll it only short distances on firm ground, in the direction of the arrow on the flange.Sources: HD 620 Part 1 A.3.3.4; HD 603 3-I, 3-L; IS 1255 7.4, p. 24; Prysmian 2024 p. 7; Nexans 2021 p. 3 (read in the standard text)
  • Store it on level, firm, well-drained ground and turn it 90° every 3 months.Sources: IS 1255 7.5, 7.6, pp. 24 to 25; Prysmian 2024 p. 8, 9; Nexans 2021 p. 8, 9; Prysmian Türkiye 3.3 (read in the standard text)
  • Leave the battens on until the cable is about to be laid: they keep off sun and knocks.Sources: HD 620 Part 1 A.3.2.5; BS 6622 D.5.2; IS 1255 7.8, p. 25; Nexans 2021 p. 11 (read in the standard text)
  • Cable ends sealed with caps in transport, storage and laying. A cap missing for over a month, or a wet end: cut back 300 mm, check for moisture and cap again.Sources: HD 620 Part 1 A.3.2.3, A.4.7; HD 603 3-I 3.2; BS 6622 C.3; BS 5467 B.4; BS 7846 A.7.4; IS 1255 7.2, p. 24; Nexans 2021 p. 7; Draka (read in the standard text)
  • Pay out tangentially, never over the flange, with the drum on an axle and jacks and braked. Top or bottom: IS 1255 says off the top; Southwire chooses by where the cable goes (the bottom into a floor conduit, the top into a tray); Nexans Belgium says the bottom, for safety.Sources: HD 620 Part 1 A.4.5; IS 1255 8.2, 8.3, 10.2; Southwire 2005 p. 2 to 3; Nexans Belgium FAQ; Prysmian 2024 p. 10; Draka p. 5, 9 (read in the standard text)
  • High voltage drums: lift by crane with a certified spreader bar, do not roll heavy drums and never stack them.Sources: HD 620 Part 1 A.3.3.2, A.3.3.4; Prysmian 2024 p. 6; Nexans 2021 p. 3; Reka p. 4 (read in the standard text)
  • Nexans: Over 10 t of cable: steel drums; wooden drums carry up to 10 t.Sources: Nexans 2021 p. 2 (maker's document)

Sheath test after laying

  • IEC 60840: A d.c. test of the oversheath to IEC 60229 Clause 5, worded as in IEC 60502-2.Sources: IEC 60840 16.1, 16.2 (read in the standard text)
  • IEC 60229: Installed cable: 4 kV per mm of oversheath thickness, at most 10 kV, for 1 minute (factory test 8 kV per mm, at most 25 kV).Sources: IEC 60229 cl. 5, p. 9; 3.1, p. 6 (read in the standard text)
  • HD 620 10-F, 10-K, 12-K · BS 6622: A d.c. test of the insulation is not recommended: it may harm it.Sources: HD 620 10-F, 10-K, 12-K; BS 6622 (read in the standard text)

Get the commissioning sheet for your own cable with Pro. See Pro

Cable end preparation

The common order of the makers and standards the research found; each step names every source. The lengths depend on the kit: its own instruction decides.

Wonder which lug fits your cable, and how its screen is earthed? See them fitted on your own cable with Pro. See Pro · Members: see them fitted in the designer

  1. Check the kit fits the cable and cut the cable square at its final position.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, pp. 1, 3, 4 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 2 (1.1) (maker's document); TEDAŞ-MLZ/99-033.B (2023) (read in the standard text)
  2. Straighten the end; heat-treat it where the maker says so.Sources: powerandcables.com, 132 kV termination masterclass (secondary source)
  3. Remove the outer sheath and any graphite or semicon coat; abrade and clean the sheath next to the cut.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 4 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 2 (maker's document); powerandcables.com, 132 kV termination masterclass (secondary source)
  4. Cut back the armour and the bedding; carry the armour across the joint or bond it to earth.Sources: Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 4 (maker's document); TEDAŞ-MLZ/99-033.B (2023), 2.2.2 (read in the standard text)
  5. Fold the screen wires back over the sheath, or cut the tape screen; bind them and form the earth lead. HV: open the metal sheath.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 4 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 3 (maker's document); BS 6622:2007, Annex C.6 (read in the standard text); powerandcables.com, 132 kV termination masterclass (secondary source)
  6. Peel the insulation screen back to its cut-back without cutting into the insulation. HV: finish with glass and taper the screen end.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 4 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 3 (maker's document); powerandcables.com, 132 kV termination masterclass (secondary source); IEC 60502-2:2014, 19.23.3 (read in the standard text); BS 6622 Annex I (read in the standard text)
  7. Smooth the insulation: no conductive traces, no nicks. HV: polish to the maker's grit and measure the diameter.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); powerandcables.com, 132 kV termination masterclass (secondary source); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 6 (maker's document)
  8. Cut the insulation back for the lug or connector without nicking the conductor.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 7 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 3 (maker's document)
  9. Clean from the cable end towards the insulation screen, never the other way.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); powerandcables.com, 132 kV termination masterclass (secondary source); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 6 (maker's document)
  10. Fit the stress control over the screen end: tape, mastic or tube, or a moulded cone.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 6 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 4 (maker's document); TEDAŞ-MLZ/99-033.B (2023) (read in the standard text); powerandcables.com, 132 kV termination masterclass (secondary source)
  11. Crimp or bolt the lug or connector; file sharp edges and fill the gaps.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 7 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 3 (maker's document); Klauke die HD 13, DIN 46235 die codes (maker's document)
  12. Shrink, push on or cold shrink the insulation and outer protection; fit sheds outdoors and keep the clearances.Sources: Ensto PEM1093ENG 2017-04, HIT1 / HOT1 12 to 36 kV (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); Nexans Euromold IS 24CSJ2-E-09, 12 and 24 kV (maker's document); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, pp. 7 to 9 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, pp. 4 to 5 (maker's document)
  13. Earth the screen and the armour. HV: run the bonding leads to the link box.Sources: BS 6622:2007, Annex C.6 (read in the standard text); TEDAŞ-MLZ/99-033.B (2023), 2.3.1 (read in the standard text); Prysmian Assembly Instructions 81006A (2022), MST 12 to 36 kV, p. 5 (maker's document); Nexans Italia IM1778DI.1, MONOi / MONOe-1, p. 5 (maker's document); TE Raychem ESD-5243-AU-10/09, OXSU-F 36 kV (maker's document); powerandcables.com, 132 kV termination masterclass (secondary source); IEC 60840:2011, Annex G (read in the standard text)
  14. Test the cable after installation.Sources: IEC 60502-2:2014, clause 20 (read in the standard text); IEC 60840:2011, clause 16 (read in the standard text); HD 620 S3:2023 (read in the standard text)

Want to see this for your own cable, with the cut-back lengths? Cable end preparation in the cable designer · See Pro